card header iconMeasure B Projects Completed to Date

Project:  Nevada Union High School - Don Baggett Theatre & Music/Choir Building Stucco Repair and Painting of Building, Exit/Roll-up Doors, Student Lockers and Railing 
Completed:  July 11, 2017
 
Project:  Nevada Union High School - Re-roofing of Buildings C & J (Bldg. C: Home Economics, Computer Lab, Special Education; Bldg. J: Math, Arts, Social Studies) 
Completed:  July 11, 2017
 
Project:  Nevada Union High School - Gas Pipeline Replacement (Facility & Water Heating) 
Completed:  August 4, 2017
 
Project:  Bear River High School - Create Two Openings between the Ag. Mechanical Shop and the Woodworking Shop, Adding Fire Shutter Doors (Roll-up doors) at the Openings
Completed:  August 21, 2017
 
Project:  Nevada Union High School - Re-roofing of Building E and the Don Baggett Theatre Complex (Bldgs. K & L)
Completed:  August 28, 2017
 
Project:  Nevada Union High School - Replace Football Field Artificial Turf
Completed:  October 20, 2017
 
Project:  Replacement of Front-End Public Address System - Two Sites
- Bear River High School 
- Nevada Union High School 
Completed: October 20, 2017
 
Project:  Addition / Replacement of Surveillance System Cameras and Associated Equipment - Three School Sites
- Bear River High School 
- Nevada Union High School 
- Silver Springs High School
Completed: 100% complete as of January 2, 2018 (minor verifications & camera adjustments to be made)
 
Project:  Nevada Union High School - Removal & Disposal of Two Decrepit Portable Buildings 
Completed:  January 3, 2018