Location: Bear River High School
Description: New All-Weather Track, Site Drainage, Path of Travel & Accessibility Improvements
Contractor: Lamon Construction (Site Preparation); Beynon Sports (Track & Field Event Surfacing)
Start Date: March 27, 2018 Completion Date: August 10, 2018 (NLT)
Worker Welding Gate Opening Mechanism
Worker Cutting Off Excess from Connectors
Steam Visible from Hot Asphalt
Team of Workers - Asphalt Paving of Track Subsurface
Workers Compacting Asphalt in East 'D' Zone
Workers Putting Finishing Touches on Asphalt before Compaction
Conveyor Scooping Up Asphalt and Transferring to the Hopper
Forms Placed for Concrete Sidewalk from ADA Parking and Path to Restroom
Worker Removing Concrete Splatter from Fence Posts and Other Workers Staging Additional Fencing Materials
Workers Pouring Concrete Around Track Outer Curb Fence Posts
Worker Ensuring Fence Post is Upright and the Correct Distance from the Sidewalk
Worker Using Post Hole Digger for Fence Posts
Worker Using Post Hole Digger for Fence Posts
Workers Installing Forms for Track Outer Concrete Curb
Project Inspector Reviewing Concrete Mix Documentation from Driver
Worker Connecting Drain Inlet Before Concrete Pouring
Workers Making Final Preparations to Sidewalk Forms in Front of visitors' Bleachers Before Concrete Truck Arrives
Forms Placed for Pouring Concrete Sidewalk Adjacent to Snack Shack
Workers Measuring Distance from Inner Track Curb
Workers Pouring and Finishing Concrete Sidewalk in Front of Home Bleachers
Motor Grader Operator Grading Asphalt Subsurface (Asphalt is Underneath Track Surface)
Dump Truck Operator Unloading Rock for Asphalt Subsurface
New Irrigation Layout for Existing Celebration Bermuda Turf
Worker Forming Curbs for Concrete Pouring in Long and Triple Jump Areas
Workers Pouring Concrete at Track Inner Curb
Workers Hammering Concrete Forms to Release Air to Aid in Concrete Settling
Workers Troweling Concrete Poured for Track Inner Curb
Close-up of Tractor Operator Releasing Rock for Backfill in Storm Drain Trench
Tractor Operator Backfilling Rock in Storm Drain Trench
Tractor Operator Using Leveling Attachment for Soil Under Future Track
Tractor Operator Using Sheeps' Foot Compactor Attachment to Compact Drainage Trench
Workers Rolling Out Geogrid Mesh for Soil Stabilization
Excavator and Compactor Operators Working Together to Compact Soil Over Geogrid Mesh
Bulldozer and Compactor Operator Working Together to Grade the Surface
Track Curbing Being Formed
Forms for Concrete Track Curb
Soil Scarification to Help in Removing Excess Moisture
Excavator Operator Digging Storm Drain Trench
Skidsteer Operator Removing Rocks in Area Being Graded
Bulldozer Operator Scarifying (~Tilling) Soil
Tractor Operator Backfilling Rock in Storm Drain Trench
Rocks Removed During Grading Operations
Operator Bulldozing Soil in Preparation for Compaction
Tracer Tape - Installed Over Drainage Pipe for Locating in the Future
Measuring Depth of Trench for Drainage Pipe Installation
Board of Trustees, Superintendent Johnson & Athletic Director Ganskie at 'Groundbreaking' Ceremony - April 11th, 2018
Principal Besler Stating What the Track Means to the School and Thanking Voters for Approving Measure B
Board of Trustees, Superintendent Johnson & Athletic Director Ganskie at 'Groundbreaking' Ceremony - April 11th, 2018
Skidsteer and Paddlewheel Scraper Operator Working Together to Remove Excess Soil
Tractor Operator Pulling a Float with Ripper for Minor Cutting and Leveling
Bulldozer Operator Giving Paddle Wheel Scraper a Push
Paddle Wheel Scraper Removing Soil and Turf
Bulldozer Operator Removing Turf in the "D Zone"
Bulldozer Operator Preparing Soil for Removal by Paddle Wheel Scraper
Tractor Operator Loading Concrete Chunks for Offsite Disposal
Workers Digging to Expose Irrigation Lines
Canine "Navigator"
Tractor Operator Leveling Soil
Concrete Borders Removed from "Old" Decomposed Granite Track
Tractor Operator Loading "Old" Track Cement Borders for Disposal
Worker Marking Underground Lines (USA)
Supervisor Reviewing Demolition Plans
View of "Old" Decomposed Granite Track
View of Stadium Entry