Timeline
 
 June 25, 2015
Board of Trustees' Approval of the 2016 Facilities Improvement Plan
June 29, 2016
Board of Trustees took action to place a General Obligation Bond, Measure B, on the November 2016 ballot
November 8, 2016
Measure B passed by voters - Thank you!
January 11, 2017
Board of Trustees selected the citizen members of the Bond Oversight Committee to serve a 2-year term
February 8, 2017
Siteline Architecture, located in Nevada City, is selected by the Board of Trustees as the District's architect for Measure B projects 
June 12, 2017
Construction begins on Measure B projects
 November 14, 2018 DCA Architects, based in Stockton, is selected by the Board of Trustees as the District's 2nd architect for Measure B projects