Timeline
 
 June 25, 2015
Board of Trustees Approval of the 2016 Facilities Improvement Plan
 
June 29, 2016
Board of Trustees took action to place a General Obligation Bond, Measure B, on the November 2016 ballot
 
November 8, 2016
Measure B passed by voters - Thank you!
 
January 11, 2017
Board of Trustees selected the citizen members of the Bond Oversight Committee to serve a 2-year term
 
February 8, 2017
Siteline Architecture, located in Nevada City, is selected by the Board of Trustees as the District's architect for Measure B projects 
 
June 12, 2017 Construction begins on Measure B projects